We’re writing to inform you that maintenance will be performed at the Lightwave Data Center beginning on Monday, March 19, 2018.

Type of Maintenance: Electrical

Location: LWDC – 9305 Lightwave Ave, San Diego, CA.

Purpose: AIS electrical engineers will perform upgrades and retrofit alternate source feed To ASTS-PDU 1A2 to ensure all systems can provide continuous sustainable support.

High Level Summary: Beginning on March 19, 2018, AIS will be retrofitting the alternate source feed to ASTS-PDU 1A2; the primary source will remain in service all all supported Power Distribution will remain energized on UPS.

The replacement source feeder is expected to take approximately (2) days to complete.

Upon completion of installation, AIS will test the new source by performing a transfer of sources at the ASTS-PDU.

Window Start: 3/19/2018 – 6:30 AM PDT
Window End: 3/21/2018 – 6:00 PM PDT

Service Impact: This maintenance is not expected to be service impacting.

Schedule: The window for maintenance is scheduled to begin at 6:30 AM on Monday, March 19, 2018 and end no later than 6:00 PM on Wednesday, March 21, 2018. The actual period time of work should not exceed 12 hours per day, however should additional time be required, notice will be provided and the maintenance window will be expanded.

Testing & Planning: All testing and planning being conducted during this window is part of a pre-defined checklist designed by the AIS electrical engineering team and consistent with IEEE and UL standards.